So you've decided to remodel your kitchen — congratulations. Now comes the question every homeowner asks within about five minutes of making that decision: how long is this actually going to take? The honest answer depends on the scope of your project, but most full kitchen remodels in the US take somewhere between six weeks and six months from first measurement to final cleanup. That range sounds huge, but once you understand what's happening in each phase, it starts to make a lot more sense.
The 30-second verdict
Skip the scroll — this is the answer.
Why the Timeline Varies So Much
Two kitchens can look nearly identical in scope and still take very different amounts of time to complete. The biggest variables are permitting speed in your municipality, contractor availability, and — critically — how long it takes your appliances and cabinets to arrive. Custom or semi-custom cabinetry can have lead times of 8–14 weeks on its own. Ready-to-assemble (RTA) shaker cabinets, by contrast, can ship in days, which is one reason so many savvy remodelers are choosing them.
Appliance lead times also vary more than most homeowners expect. A full appliance package ordered from a stocking dealer can arrive in one to two weeks; special-order finishes or configurations may take longer. Getting your design locked in and your orders placed before demolition begins is the single biggest thing you can do to shorten your overall timeline.
Phase 1: Planning & Design (Weeks 1–4)
Most experienced contractors and designers will tell you: the planning phase is where your timeline is either protected or destroyed. This is where you finalize your layout, choose your cabinets and appliances, pull permits if needed, and lock in your contractor's start date. Rushing this phase almost always creates delays later.
For cabinets, a careful plan makes a real difference. Book a free design consultation by phone, text or video and we'll walk through door styles, finishes, and hardware with you and put together a full layout and quote before you commit. You can also explore options ahead of time using our online kitchen visualizer to experiment with colors and configurations from home.
By the end of Week 4, you should have: a finalized floor plan, cabinet order placed, appliances ordered, contractor start date confirmed, and permits submitted (or already in hand, if your project doesn't require them).
Phase 2: Ordering & Lead Times (Weeks 2–8)
This phase overlaps with planning and is where many remodels quietly fall behind schedule. The key rule is order everything before demo day. If you start demolition and then discover your range has a six-week lead time, your kitchen will sit gutted and unusable for over a month.
Ranges, refrigerators, and hoods from brands like ZLINE and Forno are typically stocked by authorized dealers and can ship quickly, but confirm availability before scheduling your demo. For RTA cabinet lines like Forevermark and Fabuwood, lead times are generally much shorter than custom options — often one to two weeks after design approval.
Phase 3: Demolition (Days 1–5 of Construction)
Once permits are in hand and all materials are confirmed on order (or already in your garage), the fun part begins. Demo is typically the fastest phase of any remodel — most kitchens can be fully stripped in two to five days depending on size and complexity. This includes removing old cabinets, appliances, flooring if planned, and any walls being modified.
If you're moving a gas line or relocating a sink, rough-in plumbing and gas work happen immediately after demo, before anything else goes in. This is also when electrical rough-in work occurs — adding circuits for a new range, hood, or refrigerator. These trades need to be pre-scheduled because waiting even a few days for a plumber or electrician can stall everything that follows.
Phase 4: Cabinet Installation (Weeks 1–2 of Construction)
Cabinet installation is the structural backbone of your new kitchen, and it needs to happen in the right sequence. Upper cabinets go first, then lowers, then filler pieces and trim. A skilled crew can typically install a full kitchen of RTA cabinets in two to four days. The real time sink here isn't installation — it's waiting for inspections if your project required permits for the rough-in work.
Choosing RTA shaker cabinets that arrive pre-assembled or flat-pack with clear instructions can meaningfully speed up this phase compared to fully custom cabinetry, which sometimes requires on-site adjustments and longer punch-list periods.
Phase 5: Countertops, Appliances & Finishing (Weeks 2–4 of Construction)
Once cabinets are set and leveled, the countertop fabricator comes out to template. Stone slab countertops — quartz, granite, marble — typically take two to four weeks from template to installation. This is a fixed waiting period you can't rush, so plan around it. Laminate or butcher block countertops can often be installed in days if you're willing to trade fabrication time for material choice.
Appliances get set in place after cabinets are installed but before countertops in many cases, since the countertop fabricator needs to measure around the range cutout and hood position. Final appliance connections — gas hookup, electrical, water line for the refrigerator — happen once countertops are in and inspections are complete. This is also when your wall mount range hood gets permanently mounted and ducted.
The finishing stretch includes backsplash tile, lighting, hardware, touch-up paint, and flooring if it wasn't done before cabinet install. This phase feels fast after weeks of construction, but small punchlist items have a way of dragging out — budget an extra week at the end for final details and inspections.
Realistic Total Timelines at a Glance
The Most Common Causes of Delay (And How to Avoid Them)
Most kitchen remodels that run significantly over schedule do so for the same handful of reasons. Permit delays are the most common and the hardest to control — but submitting complete, accurate applications the first time helps. Contractor scheduling gaps are the second most common: if your electrician and plumber aren't coordinated, you can lose a week waiting for each.
Material delays — especially for cabinets ordered with incorrect dimensions or appliances backordered after demo begins — are the most preventable. The fix is simple but requires discipline: don't schedule demo until everything is confirmed on order and lead times are accounted for. It also helps to have your appliance dimensions verified before cabinets are ordered, so your range, refrigerator, and hood all fit exactly as designed.
Book a free design consultation by phone, text or video — or start online. We'll help you choose cabinets, layout your kitchen, and confirm appliance fit before you commit to a thing.
Get a Free Design Quote or call (844) 441-2003Frequently Asked Questions
Can I live in my home during a kitchen remodel?
Yes, most homeowners stay in place during a kitchen remodel, though it's inconvenient. Set up a temporary kitchen in another room — a folding table, microwave, coffee maker, and mini fridge go a long way. The hardest stretch is usually the two to three weeks between demo and when the new appliances are connected and functional.
How far in advance should I order kitchen appliances?
Order appliances at the same time you place your cabinet order — ideally four to eight weeks before your planned demo date. If you're buying stocked appliances from an authorized dealer, two to three weeks may be enough buffer, but always confirm availability in writing. For special-order finishes or professional-grade configurations, give yourself ten or more weeks to be safe.
Do I need a permit for a kitchen remodel?
It depends on what's being changed. Replacing appliances and cabinets in the same locations typically doesn't require a permit in most US municipalities. Moving plumbing, gas lines, or electrical panels — or removing walls — almost always does. Check with your local building department before demo begins; working without a required permit can complicate a future home sale.
What's the fastest type of kitchen remodel?
A straight appliance swap — replacing existing appliances with new ones of the same size and fuel type, with no cabinet or structural changes — is the fastest option, often completable in one to three weeks from order to installation. Adding RTA cabinets to that scope extends the timeline to roughly six to ten weeks, but still moves much faster than a full custom gut remodel.